The first floor is really starting to take shape with the placement of the steel.
New 4 story multi-family student housing project coming to Btown in August 2013. This new building will have 20 units altogether with a mix of 1 BR and 2BR units. Unique in it's design, this building will have a very 'uptown' vibe with it's chic curb appeal and custom interior design.
Monday, February 25, 2013
Tuesday, February 19, 2013
Steel erection
Bar joists and beams delivered and being installed this week. Weather today is frigid with sharp wind gusts. Great progress, the crew is working hard.
Tuesday, February 12, 2013
Monday, February 11, 2013
Masons working like crazy. Ground floor starting to take shape
North and South pods taking shape. Progress has been steady. Weather will be decent this week. High today of 43.
Friday, February 8, 2013
North pod going up
With the south pod topped out work has started on the north pod. Steel will be delivered next week. Weather conditions mild all week.