Monday, February 25, 2013

Structural Steel

The first floor is really starting to take shape with the placement of the steel.







Tuesday, February 19, 2013

Steel erection

Bar joists and beams delivered and being installed this week. Weather today is frigid with sharp wind gusts. Great progress, the crew is working hard.







Monday, February 11, 2013

Masons working like crazy. Ground floor starting to take shape

North and South pods taking shape. Progress has been steady. Weather will be decent this week. High today of 43.









Friday, February 8, 2013

North pod going up

With the south pod topped out work has started on the north pod. Steel will be delivered next week. Weather conditions mild all week.