Tuesday, April 23, 2013

Limestone Facade

The look is changing. Placement if limestone panels on west elevation underway.





Tuesday, April 16, 2013

Progress in mid April

Limestone Panels being placed, drywall on 4th floor, EIFS installed with color adds some detail to elevation. Things are going well and moving along...