Last day January, temps today in high 20's with low tonight of 7 deg. Masons topping of lower level in south pod, excavation started on north pod. Suppose to pour footings this weekend.
New 4 story multi-family student housing project coming to Btown in August 2013. This new building will have 20 units altogether with a mix of 1 BR and 2BR units. Unique in it's design, this building will have a very 'uptown' vibe with it's chic curb appeal and custom interior design.
Thursday, January 31, 2013
Wednesday, January 23, 2013
Saturday, January 19, 2013
Friday, January 18, 2013
Thursday, January 17, 2013
Tuesday, January 15, 2013
Marketing Boards
Marketing set up in the office. We are ready to start the leasing process, thanks to Sheila. Nice work.
Footing Excavation
After a very rainy weekend, Monday brought about frigid temps and the excavation of footers on south building pad. The crew also started on north retaining wall.
Tuesday, January 8, 2013
Friday, January 4, 2013
Thursday, January 3, 2013
Wednesday, January 2, 2013