Thursday, January 31, 2013

Starting on north pod

Last day January, temps today in high 20's with low tonight of 7 deg. Masons topping of lower level in south pod, excavation started on north pod. Suppose to pour footings this weekend.





Wednesday, January 23, 2013

Scaffold erection

The temps are a bit more bearable this week after frigid temps Monday and Tuesday.



Saturday, January 19, 2013

Tuesday, January 15, 2013

Marketing Boards

Marketing set up in the office. We are ready to start the leasing process, thanks to Sheila. Nice work.



Reinforcing footings









Footing Excavation

After a very rainy weekend, Monday brought about frigid temps and the excavation of footers on south building pad. The crew also started on north retaining wall.







Tuesday, January 8, 2013

Friday, January 4, 2013

Thursday, January 3, 2013

The building is down

Good progress on the demo work. They will start on the site work early next week.









Wednesday, January 2, 2013